Paver calculator
How many pavers for a patio or path, and how much base stone and bedding sand to order.
How it works
Each paver takes up its own size plus half a joint on every side, so we divide the area by (length + joint) × (width + joint), then add an allowance for the pavers you'll cut at the edges. The base and sand are the area × their depth, plus extra because loose stone and sand settle when you compact them. Weights use about 1.6 tonnes per cubic metre, which you can change.
Worked example
A 12 × 10 ft patio in 4 × 8 in pavers with ⅛ in joints, laid in running bond:
- Each paver plus joint covers 8.125 × 4.125 in = 33.5 sq in, so 120 sq ft takes 516 pavers. With 5% for cuts, buy 542.
- A 4 in base with 20% for compaction is 1.78 cu yd (about 2.4 tons). A 1 in sand bed is 0.44 cu yd.
A metric example: a 4 × 3 m patio in 200 × 100 mm block pavers laid herringbone, with 3 mm joints, takes 632 pavers including 10% for cuts, 1.44 m³ of sub-base (about 2.3 tonnes) and 0.43 m³ of sand.
How deep should the base be?
For footpaths and patios, a compacted base of about 4–6 in (100–150 mm) of crushed stone under 1 in (25–30 mm) of bedding sand is common. Driveways and soft or clay soils need a deeper base. Paver makers publish base depths for each product and use, so check theirs before you dig.
Which pattern wastes most?
Stack bond, running bond and basketweave leave straight edges, so cuts are few: about 5% is usually enough. Herringbone and other angled patterns need a cut on almost every edge paver: allow 10% or more. Curved edges add cuts too. Keep a few spare pavers for repairs, since colours change between batches.
Common questions
How many pavers per square foot?
For 4 × 8 in pavers, about 4.5 per sq ft without joints and about 4.3 with ⅛ in joints. Larger pavers need fewer: divide 144 by the paver's area in square inches.
How many pavers per square metre?
200 × 100 mm block pavers come to 50 per m² without joints, or about 48 with 3 mm joints. Add your allowance for cuts.
How much sand do I need under pavers?
For a 1 in (25 mm) bed, about 0.1 cu yd per 30 sq ft, or 0.025 m³ per m², plus extra for compaction. Joint sand is separate and much less.
Reviewed by Alex Rowan, Editor. Last reviewed . How we calculate · Report a problem